|
Financial
Operations Last
revised:
07/13/2004
The overhead rates for federal awards and sub-awards are
determined in accordance with the provisions of section G-7
of the OMB
Circular A-21 (effective May 1996). Federal policy requires
fixing rates for the life of the award at rates in effect
(including negotiated provisional rates that will be revised
when the federal rates are negotiated) at the time of the
award. See OSP's policy Implementation
of "Fixed Rate" Requirements of A-21. Most non-federal
awards are established at MIT billing rates which change each
FY to the current FYs federal negotiated rates. However,
both federal and nonfederal sponsors occasionally specify
a rate and/or base which differs from those which would normally
be applied under federal and/or Institute policies. This document describes the practices for departments, laboratories
and centers (DLCs) related to handling overhead information
on research WBS elements. It particularly focuses on situations
where underrecovery (U/R) of overhead occurs (other than U/R
resulting from Federal A-21 "Fixed Rate" requirements
or Training Grants). U/R may occur in any research WBS element
where overhead specifications are established at less than
the current federal negotiated rates. See OSP's Indirect
Cost Rates page on the web.
Note
Overhead
(OH) is also referred to as Facilities and Administration
(F&A) costs or Indirect costs. The terms overhead
and F&A will
be used interchangeably throughout this document.
MIT prefers the term F&A to be consistent with
the Federal government, but the SAP system refers
to overhead. With proposal preparation, DLCs complete most research budgets
utilizing current federal negotiated research overhead rates
on a modified total direct cost (MTDC) base. However, occasionally
sponsor policies dictate a rate and/or base that will result
in overhead recovery below that which would be produced using
the federal negotiated research rates. When this occurs, the
DLC also prepares an estimate of the U/R of overhead for each
year of the project period. This estimate is for internal
purposes only and is not submitted to the sponsor with the
proposal. On the MIT Proposal Summary Form, the DLC enters the appropriate
overhead rate and base, reflecting sponsor limitations. The
anticipated U/R of overhead for each year of the proposal
is noted along with the source of funds identified to cover
the U/R. The funding source may be one or more of the following
(see below). If a funding source other than the following
is negotiated, please email CAO at ur-issues@mit.edu
to determine the correct journal entries to process funding. *The use of released general for F&A U/R requires
approval by a representative of the appropriate Dean.
A copy of every cover sheet for proposals incurring U/R,
independent of funding source, should be sent to Charlene
Placido, VPRs Office, 3-240; for the School of Humanities,
Arts, and Social Sciences, the proposals incurring U/R should
also be routed to Charlene. OSP administrators are responsible for determining and entering
the costing
sheets and rates on Coeus input sheets. If the WBS element
will incur U/R (other than U/R resulting from Federal A-21
"Fixed Rate" requirements or Training Grants), OSP
administrators are also responsible for entering by Project
Year the U/R amount and source of funding as entered on the
MIT Proposal Summary Form. See the OSP
documentation on Research WBS Elements. Overview Monthly, DLCs review the Summary Statements to verify accuracy
of all entries. The F&A cost elements are used as follows:
Note
A
cost element and a G/L account are often synonymous.
See the
Glossary. The SAP costing sheets post the system calculated F&A
at MIT billing rates to the following cost elements: 600304
F&A On
600305
F&A Off
If the wrong costing sheet had been assigned resulting
in an error in the posted MIT billing rate amount, a JV
must be prepared by CAO to correct the billing rate amount.
Since manual JV entries cannot post to 600304 or 600305
(6-series cost elements), the following (4-series) cost
elements are used: 490310
Correct Current Yr F&A
On
490311
Correct Current Yr F&A
Off
490312
Correct Prior Yr F&A
On
490313
Correct Prior Yr F&A
Off
Note
The
SAP system uses the 6-series cost elements for
posting system calculated costs such as F&A,
EB, or settlements. Manual entries such as JV's
cannot post to the 6-series cost elements, but
instead must use the corresponding 4-series cost
elements. If the sponsor funds F&A
at a base/rate other than MIT
billing rates, the SAP costing
sheets post an adjustment to
the billing rate amount (cost
elements 600304-600305) to net
F&A
to the sponsor's base/rate amount
using the following cost elements: 600316
Adj F&A
On to Spon Base/Rate
600317
Adj F&A Off to Spon
Base/Rate
If the wrong costing sheet and/or adjustment key had been
assigned resulting in an error in the posted adjustment
amount, a JV must be prepared by CAO to correct the adjustment
amount. Since manual JV entries cannot post to 600316 or
600317, the following cost elements are used: 490318
Adj CY F&A On to
Spon Base/Rate
490319
Adj CY F&A Off to
Spon Base/Rate
490320
Adj PY F&A On to
Spon Base/Rate
490321
Adj PY F&A Off to
Spon Base/Rate
Note
CY
(Current Year) is used for posting adjusting F&A
calculations applicable to the current MIT fiscal
year F&A. If a costing sheet has not been
created for a sponsor's base, OSP
will assign a costing sheet that
most closely matches the sponsor's
base. Since the sponsor's base for
F&A is different
than the costing sheet base on which
the sponsor's F&A is
being calculated, OSP will enter
a note in Coeus and notify CAO
to process a JV to manually adjust
the F&A to the sponsor's
base/rate. Within two weeks of monthly
closing, CAO will calculate and
post these F&A adjustment JV entries.
After posting CAO will email to
DLCs the JV document number for
the adjusting JV entries. If you
have a WBS that has been assigned
a costing sheet that only approximates
the sponsor's base, please wait
for CAO email notice before funding
the U/R for this type WBS. (Note:
Until CAO adjustment entries post,
the F&A U/R
amount and the WBS uncommitted balance
will not be accurate.) If the F&A
at billing rates has correctly posted
to the WBS element but the total
net F&A charged to sponsor is incorrect
as a result of the assignment of
a costing sheet that only approximates
the sponsor's base, CAO will process
the following JV entry: If the net F&A is understated, Cost Object
Cost Element Name
Debit
WBS Element
Adj CY F&A to Sponsor
Base/Rate
Credit
DLC U/R Cost Center
Adj CY F&A to Sponsor
Base/Rate
If the net F&A is overstated, Cost Object
Cost Element Name
Debit
DLC U/R Cost Center
Adj CY F&A to Sponsor
Base/Rate
Credit
WBS Element
Adj CY F&A to Sponsor
Base/Rate
OSP is responsible for assigning and correcting a WBS elements
costing sheet and adjustment keys and notifying DLCs of corrective
action via a Coeus NoA. For all changes to costing sheets
and/or adjustment keys, monthly CAO reviews the financial
data to determine whether overhead charges posted to the cost
object need to be corrected. Within two weeks of month-end
close, CAO is responsible for calculating and processing the
necessary overhead corrections to posted F&A resulting
from the assignment of a wrong costing sheet and/or adjustment
key. After posting JV entries, CAO will email the JV document
number to the DLC. For DLCs that incur U/R in FY00,
effective FY01 a DLC cost center
will be created to which the DLCs
U/R will post. (In SHASS
and SA&P, only
one cost center will be created
and monitored by the relevant Dean's
Office.) U/R resulting from Federal
A-21 "Fixed
Rate" requirements and Training
Grants post directly to the Institute,
not to the DLCs U/R cost center. If an F&A U/R cost center
has not been created for a DLC
(other than SHASS and SA&P DLCs)
and the DLC incurs U/R in the future, the VPR Office
(when in receipt of an MIT Proposal
Summary Form with F&A U/R)
will notify DLCs to: DLC U/R Cost Center Monthly, DLCs will: Adj
F&A On to Spon Base/Rate
600317
Adj
F&A Off to Spon Base/Rate
and
Cost Object
Cost
Element
Cost Element Name
Debit
DLC Discretionary
800704
F&A UR Funded Transfer
Out
Credit
DLC U/R Cost Center
800703
F&A UR Funded Transfer
In
Cost Object
Cost
Element
Cost Element Name
Debit
VPR Cost Center 1733000
800704
F&A UR Funded Transfer
Out
Credit
DLC U/R Cost Center
800703
F&A UR Funded Transfer
In
Cost Object
Cost
Element
Cost Element Name
Debit
VPR Cost Center 1733000
800704
F&A UR Funded Transfer
Out
Debit
DLC Discretionary
800704
F&A UR Funded Transfer
Out
Credit
DLC U/R Cost Center
800703
F&A UR Funded Transfer
In
FY Released general funds should be expended prior
to charging U/R to the VPR U/R Budget:
Cost Object
Cost
Element
Cost Element Name
Debit
DLC General
800704
F&A UR Funded Transfer
Out
Credit
DLC U/R Cost Center
800703
F&A UR Funded Transfer
In
WBS U/R that exceeds the released general funds
will be funded by the VPR U/R Budget.
Cost Object
Cost
Element
Cost Element Name
Debit
VPR Cost Center 1733000
800704
F&A UR Funded Transfer
Out
Credit
DLC U/R Cost Center
800703
F&A UR Funded Transfer
In
Sponsor's facility costs funding should be expended
prior to charging U/R to DLC Discretionary:
Cost Object
Cost
Element
Cost Element Name
Debit
WBS Element
420316
Other
Sponsor Funded Costs -not MTDC
Credit
DLC U/R Cost Center
420316
Other
Sponsor Funded Costs -not MTDC
WBS U/R that exceeds the facility costs (Other
Sponsored Funded Costs - not MTDC) will be funded by DLC
Discretionary:
Cost Object
Cost
Element
Cost Element Name
Debit
DLC Discretionary
800704
F&A UR Funded Transfer
Out
Credit
DLC U/R Cost Center
800703
F&A UR Funded Transfer
In
490318
Adj CY F&A
On to Spon Base/Rate
490319
Adj CY F&A
Off to Spon Base/Rate
490320
Adj PY F&A
On to Spon Base/Rate
490321
Adj PY F&A
Off to Spon Base/Rate
Cost Object
Cost
Element
Cost Element
Name
Debit
WBS Element
see
above
Adjust F&A
to Sponsor Base/Rate
Credit
DLC U/R Cost Center
see
above
Adjust F&A
to Sponsor Base/Rate
Cost Object
Cost
Element
Cost Element Name
Debit
DLC Discretionary
800702
Cost Sharing-Transfer
Out
Credit
WBS Element
800701
Cost Sharing-Transfer
In
Debit
WBS Element
420317
Cost
Shared F&A Underrecovery - not MTDC
Credit
DLC U/R Cost Center
420317
Cost
Shared F&A Underrecovery -
not MTDC
Since the full years cost sharing amount is posted
to the DLCs U/R Cost Center in the first month of
the project year, the net postings for this WBS element
in the DLCs U/R Cost Center will be in credit status
until such time the actual U/R equals the cost sharing amount.
This is rare; if you have a WBS where U/R is cost sharing,
please send email to ur-issues@mit.edu
for additional guidance on processing JV entries at fiscal
year close. For guidance on preparing final June entries to clear the
U/R cost center, send email to ur-issues@mit.edu.
Reminder: The F&A U/R cost center must net to
zero at the end of each fiscal year. Therefore, funding for
June F&A U/R must be processed as a final June entry in
period 13. CAO final audit of overhead will be based
on overhead specifications in Coeus (and on legacy system
001 forms for WBS which predate SAP implementation). Any questions
CAO accountants have related to this information should be
directed to the appropriate OSP Contract Administrator and
DLC Administrator. After processing any overhead correction
entries, CAO will send email with the JV document number to
the DLC Administrator. Who
to Contact with Questions: U/R
Funding Source:
DLC
AO
Assigned
Costing Sheet and Rates:
Postings
to U/R Cost Center:
Preparing
U/R JV Entries:
Using
Data Warehouse U/R Reports:
CAO
Final Audit Entries:
The following CAO personnel receive emails addressed to To assist DLCs in monitoring U/R,
four Data
Warehouse (DW) reports have been
created. See Data
Warehouse Reports. 1.
Research F&A
U/R Cost Center 2.
Research F&A U/R
- Coeus IDC Information 3.
Research F&A U/R
- JV Template 4.
Research
F&A U/R - Change in Master
Data Web Site Description Controller's Accounting Office (CAO) Documentation for use in training CAO Sponsored Accounting
staff. Describes how secondary costs are applied within
each costing sheet. Lists the employee benefit and overhead adjustment
keys and rates. Office of Sponsored Programs (OSP) Explains how OSP handles F&A information on research
WBS elements, especially underrecovery of indirect
costs. Lists the EB on-campus and off-campus rates by fiscal
year(s). Lists F&A on-campus and off-campus rates for
research and fund accounts by fiscal year(s). U.S. Office of Management and Budget See Section G-7 for provision on fixed rates for
the life of the sponsored agreement. SAP for MIT Documentation on the Web |